South Luzon Expressway gridlock

Carmaggedon hits SLEX for the second day

account_balanceMetro News account_circleJake Cruz chat_bubble_outline0 Comments

Motorists and passengers suffered the brunt of traffic congestion along South Luzon Expressway SLEx) for the second day on Thursday, with line of vehicles extending for almost 24 kilometers from Alabang to the Eton exit in Sta. Rosa, Laguna.

A usual one hour travel from Sta.Rosa to Makati took more than theee hours Thursday, resulting in late work or school appointments.

The cause was the closure of Skyway at-grade’s outermost lane right after the Alabang Viaduct in Muntinlupa City amid the construction of pylons for the 6-km extension of the Skyway from Barangay Cupang to Susana Heights.

More than 370,000 vehicles use SLEx every day, while around 196,000 ply Skyway daily, according to data from the Toll Regulatory Board as of June.

A passenger said he spent fours hours on Thursday to get to his office in Makati from General Mariano Alvarez, Cavite province.

He had to wait for an hour for a bus at the Carmona, Cavite, toll gate of SLEx because buses had a long turnaround as a result of the gridlock.

He then spent three more hours on his commute to get to work.

“I left home at 7:30 a.m. and reached the office at 11:34 a.m.,” he said. Normally, his trip to the office takes only one and a half hours.

Mikkah Factor left her home in San Pedro, Laguna, before 8 a.m., and arrived in Susana, Alabang, at 9 a.m.

“I slept in our car and when I woke up, it was already 10:30 a.m. and I’m still in Alabang, stuck in traffic on SLEx,” Factor said.

“Usually, when I leave our house at 8 a.m., I arrive in Magallanes, Makati, where I wait for a jeepney ride to work, at 10 a.m. or sometimes before 10,” she said. “But due to that extreme traffic, I got at Magallanes at 11:30.”

As expected, social media was flooded with complaints from motorists and commuters who missed their classes, deemed absent on work or turned up hours late on their appointments.

A netizen claimed it took him three hours to clear the stretch of Mamplasan in Biñan, Laguna to Makati.

The 30-km ride takes only around an hour on a normal day.

“SLEx shouldn’t be called an expressway anymore,” she said.

Slow Luzon Expressway

Others resorted to giving SLEx alternative names, such as “Sobrang Lalang Expressway” or “Slow Luzon Expressway.”

The carmageddon came as the Asian Development Bank (ADB) reported that Manila was now the most congested natural city—those with a population of at least 5 million—out of 278 cities in Asia.

Commuters in Manila, according to the ADB report, could not even take public transport for a substantial portion of their commute, and travel by public transport takes three times as long compared with using private cars.

The ADB report based its findings on a random sampling of hot spots in each city and on Google Maps to determine the travel time between these locations during peak hours.

South Road, Baybayin

Cars swarmed on Manila South Road as well as Muntinlupa’s Baybayin (network of streets by Laguna de Bay) as an alternative to SLEx, the main artery connecting Calabarzon and Metro Manila.

In a tweet on Thursday, Muntinlupa Rep. Ruffy Biazon said the SLEx gridlock spilled over to Manila South Road, the city’s national road that runs almost parallel to SLEx and connects to the expressway in Alabang and Susana.

Stop-and-go, zipper lane

“We are under threat of shutting down,” Biazon said.

San Miguel Corp. (SMC) Tollways—operator of SLEx and Skyway—admitted that the ongoing construction project was to blame for the carmageddon, which persisted day and night, even on nonpeak hours.

For the meantime, a “stop-and-go” traffic scheme would be implemented on the East Service Road near Kawasaki Motors Corp. in Cupang for motorists to pass through.

A southbound SLEx zipper lane was also opened for counterflow.

SMC Tollways issued an apology. “When this project is finished, traffic flow will be faster and more comfortable. We are doing everything we can in order for the construction to be finished at an earlier time,” it said.

But it also asked motorists “to plan their trips … [suggesting] an hour or two lead time.”

The Inquirer reached the Toll Regulatory Board for comment, but it had yet to respond.

The construction of the Skyway Extension project in Muntinlupa began in August.

Completed by end 2020

Once completed by December 2020, the P10-billion project would extend the elevated expressway from Cupang to Susana Heights at Barangay Tunasan, also in Metro Manila’s southernmost city.

SLEx is a 51-km expressway that connects Metro Manila to the provinces of Calabarzon region. It starts on Quirino Avenue in Manila’s Paco district and goes all the way south to Santo Tomas, Batangas.

Skyway will be one of the longest flyovers in the world with a total length of 31 km when it opens its Stage 3, from Buendia in Makati to Balintawak in Quezon City, connecting with the North Luzon Expressway.

Skyway is also connected to the 11-km Naia Expressway, which leads to the terminals of  Ninoy Aquino International Airport in Pasay and Entertainment City in Parañaque.

Stage 1 of Skyway started in 1995, involving the construction of a six-lane, 10-km elevated expressway from Buendia to Bicutan in Taguig.

Stage 2 started in 2009, extending Skyway for 7 km from Bicutan to Alabang.


date_rangeDate Published
1 year ago
shareShare article
folder_openArticle tags
content_copyCategorized under

Share your thoughts with us

Related Articles

Remittances likely to rise in the coming months

account_balanceMetro Manila chrome_reader_mode12 hours ago

Gains in the vaccination program of countries where overseas Filipino workers (OFWs) are, along with economic recovery around the world, are expected to further boost remittance growth in the Philippines, according to a report by Philippine News...

House pushes Quezon-Bicol Expressway 

account_balanceMetro Manila chrome_reader_mode1 day ago

The House of Representatives on Wednesday overwhelmingly approved on final reading a measure mandating the construction of Quezon-Bicol Expressway (QUBEX) as an "integrated transport and economic development strategy” for the Bicol Region,...

Duterte leaves Ivermectin use to doctor, patient 

account_balanceMetro Manila chrome_reader_mode5 days ago

President Rodrigo Duterte has left to the medical professionals and their patients the decision to use anti-parasitic drug Ivermectin to prevent or treat the coronavirus disease 2019 (Covid-19), according to a report by Philippine News Agency. ...

Belmonte meets with economic board 

account_balanceQuezon City chrome_reader_mode1 day ago

Nagpulong ang Quezon City Economic Development and Investment Board (EDIB) sa pangunguna ni Mayor Joy Belmonte upang pag-usapan ang mga polisya at hakbang tungo sa pagpapaunlad ng ekonomiya ng lungsod. Iprinisinta naman ni Quezon City Local Economic...

Let's Stay Connected Like us on our Facebook page.
×
Click on the article to continue reading
Quezon City adopts no contact apprehension system Red Cross pushes saliva test Vaccines from COVAX to arrive in Q1 Makati Shangri-La to close doors on Feb. 1 Cities in NCR to start vaccination simultaneously Mother, girlfriend of Filipino infected with UK variant also test positive Send Press Release MNC Facebook Page MNC Twitter Page MNC Instagram Page LGU Spotlight Barangay Front Business Sports Entertainment Metro Gen Metro Feature